Friday 28th of March was a day, when first lean concrete has been laid. The site looks enormous in reality, while photos do not reflect the scale.

Two concrete pumps were needed to reach bottom part of the plot.

The view from bedrooms will be far better, than we imagined. From this view we go 2,5 meters up.

Apparently there’s a view to Lefkimmi Cap 10 kilometers away.

To understand, where we are now: on above photo a man standing on a place, where lean concrete for 120 cubic meter water tank will be placed.

The watertank will be supporting the whole house to not slip down the hill. From the surface shown below, the tank will be 2,5 meters above.



One response to “Heavy machinery enters the scene | #week 24”

  1. […] weeks: that’s how long it took to build the concrete structure. When we started at the beginning of April, it seemed that everything would already be ready in the […]